01732 454 960
Case Studies

HSBC, Worthing


Replacement of Complete AC system.

Dunn AC were appointed the contractor to replace the failing up-flow critical cooling units serving their main server room.

Work involved the de-installation, de-commission and correct disposal of existing up-flow critical cooling units. Dunn AC Supplied and installed 50kW of critical cooling by way of multi spit systems all linked to trend BMS system. This works involved a Böcker crane to lift equipment off and on to the roof.

Our task was to complete the works on a strict deadline with partial out side of normal working hours and with time restraints in place on crane lifts.

Full operation and maintenance manuals, test and commissioning certification and user training followed the successful completion.

More case studies

Some of our recent clients:

Our accreditations:

Constructionline Environment Agency BESA Logo Defra Logo Achilles Logo Altius Logo Altius Logo SSIP Logo Alcumus Logo