Dunn AC limited were asked by their client to supply replacement NG heating system for there failing aged system on site.
3X floor mounted Potterton Kingfisher NG boilers were isolated, removed and disposed of.
Pipe work modifications, flue modifications and mounting modifications were made in order to allow for 3X frame mounted modern condensing NG boilers to be installed.
Full operation and maintenance manuals, test and commissioning certification and user training following the successful completion.
More case studiesSome of our recent clients:
Our accreditations: